Engineering task & construction content: According to the rough estimate of investment, The Blueway of Guangming River has a total length of 58.6 kilometers, a construction area of 1326 hectares, and a rough estimate of the construction project is CNY 1,179,648,200.
In the core area, it is mainly to build the relevant service facilities for the slow-moving roads around the lake, the service station, and the tourist center, as well as the transformation and improvement of the current hydraulic facilities and the dam face and landscape under the dam. Because of the requirement of the water source protection, the slow-moving roads and the relevant supporting facilities are located in the expansion area, which is an important part of the project. It needs the investment of the city government and to be built in synchronization with the projects in the core area.
Work Content
Content of bid invitation: may include but is not limited to: 1. Conceptual schematic design; 2. Scheme design requires the approval of the relevant authorities; 3. Preliminary design requires the approval of the relevant authorities; 4. Construction drawing design, (including the detailed design of professional subcontract) requires reviews of the relevant departments; 5. Compilation of as-built drawing requires reviews of the relevant departments; 6. Bill of quantities, the technical part of the bidding document, and bidding drawings required for construction and equipment bid; 7. Send a design team to the construction site to provide technical services for the engineering construction, and fulfill their duties and obligations for the project quality and safety in accordance with the national rules and regulations; 8. The design extended services: including but not limited to participating in joint trail operation, regular project visits, and award declaration and cooperation; 9. Assist in the approval and application for construction, provide complete application materials, and assist in the project review, approval, audit, and filing with relevant competent departments and units; 10. Collect and purchase third-party materials related to the design of the project; 11. Undertake the review meeting of the design results at each stage, and bear the expenses incurred.
Registration Requirements
Qualification requirements:
1、Qualification requirements for the bidder:
The bidder shall have:
(1) Professional Class A and above qualification for landscape architecture engineering design.
(2) Professional Class A and above qualification for water conservancy industry (urban flood control or channel improvement).
(3) Professional Class A and above qualification for construction industry (construction engineering).
2、The consortium bid is accepted for this project and overseas design institutions are allowed to participate in the bidding. The consortium shall consist of no more than three (3) organizations. The leading unit of consortium shall have the Professional Class A and above qualification for water conservancy industries( urban flood control or river regulation)engineering design.
3、Qualification requirements for project leader: Have the title of senior engineer and above. As for the consortium’s bid, the project leader shall be appointed by the leading unit of the consortium.
Prizes
Limited price of this contract construction CNY 41,758,000.
Compensation:
Design service time: From the date of signing the contract to the completion of final acceptance, and audit of settlement and returns.
Others:
1、Conceptual scheme design:
(1)The Designer shall propose 3 conceptual schemes of international level to the tenderer for review within 60 days upon bid winning. See Attachment IV for the projects of Mill River Park and Greenway/Madrid Riverside Landscape/Chicago Riverwalk/Connection of Both Banks of Huangpu River in Shanghai for reference. The 3 schemes must be provided by 3 different teams (overseas designers allowed to join), and the Designer, if being a consortium, shall be deemed as a team.
(2)If all the schemes fail to satisfy the tenderer, the tenderer shall not pay for the schemes and be entitled to deducting 50% of the engineering design fee as liquidated damages and organize an international competition for conceptual schemes.
2、The Tenderer shall have the right to reject the submission of the bid applicant if the bidder is in the period of rejecting the bid due to his/her bad behavior recorded by the Shenzhen Water Authority prior to the bid closing (subject to the search results at http://swj.sz.gov.cn/xxgk/xmxxgk/pgt/).
The registration deadline is 2020.04.13.18:00. If you’re interested in this competition, please feel free to contact AIMIR for more following details and submit the relevant documents timely to avoid any delay.